MIL-PRF-49167B(CR)
the contractor. The results of all table III tests and any physical damage shall be used to
determine the success or failure of the reliability test. In the event of a table III test failure, the
time interval between the preceding successful test and the failure shall not contribute to the total
cumulative hours. Testing shall continue until the total hours together with the total count of
relevant equipment failures permit either an accept or reject decision in accordance with figure 6.
Only equipment "on" time shall contribute to the total unit hours. No single equipment's "on"
time shall be less than one-half the average operating time of all equipment on test.
4.7 Preconditioning. Each auxiliary control module, in a nonoperating mode, shall be
subjected to at least 20 cycles as specified in figure 3. Preconditioning may be performed before
or after conformal coating.
5. PACKAGING
5.1 Packaging. For acquisition purposes, the packaging requirements shall be as specified
in the contract or order (see 6.2). When actual packaging of materiel is to be performed by DoD
personnel, these personnel need to contact the responsible packaging activity to ascertain requisite
packaging requirements. Packaging requirements are maintained by the Inventory Control Point's
packaging activity within the Military Department or Defense Agency or within the Military
Department's System Command. Packaging data retrieval is available from the managing Military
Department's or Defense Agency's automated packaging files, CD-ROM products, or by
contacting the responsible packaging activity.
6. NOTES
(This section contains information of a general or explanatory nature which may be helpful, but is
not mandatory.)
6.1 Intended use. The auxiliary control module is intended for use in infrared systems.
6.2 Acquisition requirements. Acquisition documents should specify the following:
a. Title, number, and date of this specification.
b. Issue of DoDISS to be cited in the solicitation, and, if required, the specific issue of
individual documents referenced (see 2.2.) .
c. Packaging requirements (see 5.1).
d. First article tests are required except for existing suppliers (see 6.3.2).
(1) Time frame for submission of first article test reports when first article tests are
required.